Key takeaways
- Utility requirements change often, and many bid sets are drawn without a utility layout.
- Service point, transformer location and conduit counts are the most common surprises.
- Accurate budget numbers on the site utility scope help you win and keep the job.
Over 90% of the site utility drawings we see are incorrect. That is not a knock on engineers. Utility requirements change often, and most bid sets are drawn before the utility has issued its own layout. The result is a scope that looks clear on paper and changes after award.
Where layouts usually go wrong
| Item | What happens |
|---|---|
| Service entrance point | The utility picks a different pole, manhole or riser than the drawings show. |
| Transformer type and location | Pad mount versus vault, clearances and access change the civil work. |
| Conduit count and size | The utility spec calls for more or larger ducts than shown. |
| Primary versus secondary ownership | Who builds and owns which part is not what the bid set assumed. |
| Accommodation work | Utility charges and lead times nobody carried in the budget. |
What to check before you price
- 01Ask whether the utility has issued a layout or service letter yet
- 02Compare the drawings against the utility's current service specifications
- 03Confirm who owns and builds each piece from the property line in
- 04Flag possible accommodation charges and lead times in your proposal
- 05Get budget numbers from someone who builds these systems every week
Many of D&M's clients are other electrical contractors. We help them win jobs with accurate budget estimates on site utility scopes, and give their clients confidence by knowing these systems inside out.