Photo: D&M crews in the field.
Years before the shelter was bid, engineers had specified conduit in the new Ridge Hill Bridge to feed it. D&M was the low bidder and won the prime electrical contract. During coordination with Con Edison, the original service layout turned out to be no longer viable.
The accommodation work Con Edison required would have cost the City of Yonkers over $150,000 and taken nearly 9 months. D&M proposed an alternate layout that needed almost no utility work and no accommodation charges, intercepted the existing conduits under the bridge with its own forces, and routed the feeder to a new customer owned riser pole.
The result saved the city more than $100,000, and the service was energized in less than two months.