Case study · Municipal

Yonkers Animal Shelter service redesign

An alternate service layout that avoided over $150,000 in utility charges and had power on in under two months.

Savings to the city
Over $100,000
Utility charge avoided
Over $150,000
Energized in
Under 2 months
Customer owned riser pole with medium voltage equipment

Photo: D&M crews in the field.

Years before the shelter was bid, engineers had specified conduit in the new Ridge Hill Bridge to feed it. D&M was the low bidder and won the prime electrical contract. During coordination with Con Edison, the original service layout turned out to be no longer viable.

The accommodation work Con Edison required would have cost the City of Yonkers over $150,000 and taken nearly 9 months. D&M proposed an alternate layout that needed almost no utility work and no accommodation charges, intercepted the existing conduits under the bridge with its own forces, and routed the feeder to a new customer owned riser pole.

The result saved the city more than $100,000, and the service was energized in less than two months.