D&M Electrical Contracting, Inc.

Featured project · Commercial

Peak Power energy storage, 4 West Red Oak Lane

A turnkey energy storage unit in a 135,000 square foot office building, finished in under 60 days.

Completion
September 2018
Project valuation
Under $250,000
Construction manager
Lockheed Martin
Transformer installed in a concrete enclosure

Photo: D&M crews in the field.

4 West Red Oak Lane is a 5 story, 135,000 square foot office building. The project installed an energy storage unit that cuts the customer's peak demand charges and lets the building take part in Con Edison's demand response program for additional savings.

D&M acted as prime contractor for the installation: site work, conduit and wire, crane and rigging, switchgear and protective relay equipment, including programming and testing.

The project was completed turnkey in less than 60 days with minimal disruption to tenants, and is one of the largest energy storage installations in a commercial building in New York.

Start a project

Tell us about the job. We will tell you how we would build it.

Send drawings, a scope or a question. For an outage, call any time.